Send status: NotSent | List state: Open
Customer approved: No | Approved date: —
| Description | Status | Completed | Notes | Pic |
|---|---|---|---|---|
| HVAC Installation | Open | — | Start May 11, Target Complete May29 | — |
| Insullation | Open | — | Start June 15th, Target Complete June 19th | — |
| Ruff Wiring | Open | — | — | — |
| Finish Wiring | Open | — | — | — |
| Gas Pipe for Heater | Open | — | Schedule with Plumber with HVAC | — |
| Schedule Inspection | Open | — | Call Week of June 22 | — |
| Interior Doors | Open | — | After Sheetrock | — |
| Exterior Doors | Open | — | Order Doors, install by 6/8 | — |
| Sheetrock | Open | — | Start Week of June 22 | — |
| Trim / Baseboard | Open | — | Start wee of 7/7 | — |
| Deck (first and second floorr) | Open | — | Start 5/25 | — |
| Cellar Framing | Open | — | Start 5/27 | — |
| Misc Framing | Open | — | As needed | — |
| Landscaping | Open | — | End of July | — |